What
are the tabs in SEMAP used for?
The
tabs identify the various action steps in the SEMAP business process.
The major tabs available to HA users are: Assessment Profile, Reports,
and Submission. The major tabs available to HUD users are: Assessment
Profile and Reports.
When do I need to do my SEMAP certification?
The SEMAP certification must be submitted electronically within
the 60 days after your Fiscal Year End (FYE).
| Fiscal
Year End (FYE) |
SEMAP
Due Date (60 days later) |
| March
31 |
May
30 |
| June
30 |
August
29 |
| September
30 |
November
29 |
| December
31 |
March
1 (February 29 if Leap Year) |
Can I submit a paper SEMAP certification?
No. Generally speaking, the certification must be submitted electronically
in IMS/PIC. Exceptions must be approved by HUD headquarters in advance
and are rarely granted. One exception covers MTW agencies, which
must submit a paper certification for their MTW inventory.
What if I try to submit and there is no "Submit"
button?
This means that you do not have the proper rights in IMS/PIC to
submit the certification; the certification has not been completed;
the due date has passed and the certification period has ended;
or else it has already been submitted. Contact your agency security
coordinator to revise your rights to include submission in SEMAP.
Review each indicator and sub-section to ensure that you either
made all entries or marked them "Not applicable."
Back to top
Question
14 doesnt apply to us; can I skip it?
If
it does not apply, you must mark it "Not applicable" in
both sections 14.a. and 14.b.
What if the 60-day due date falls on a Sunday
or a holiday?
There are no changes for Sundays and holidays. IMS/PIC is
generally operational 7 days per week, 24 hours per day, except
when taken down for scheduled or emergency maintenance, which will
be announced. In addition, IMS/PIC is designed so it can be accessed
from any personal computer with an up-to-date web browser and Internet
access from anywhere in the world. The submission need not be done
from the PHA office.
Back to top
What
if I miss the 60-day due date because of PC or network problems?
HUD
headquarters will make exceptions where failure to report was beyond
the control of the PHA, but each decision must be justified on its
own merits. Generally speaking, if a PHA waits until the last minute
and discovers a problem, HUD is unlikely to grant an exception.
However, if there has been a pattern of attempting to submit the
certification, including calls to the REAC TAC help line before
the last day, HUD is more likely to grant an exception. If the HUD
SEMAP Office authorizes an exception, IMS/PIC will open the submission
window for that PHA for a brief period (2-3 business days).
What does it mean when my SEMAP says we are
"Troubled"?
It means that your PHA has received an assessment score below 60
percent. SEMAP "Troubled" status carries special action and reporting
requirements and may not be removed without a confirmatory review
by the field office.The PHA will remain in "Troubled" status until
completion of a confirmatory review conducted by the field office
even if its score the following year is greater than 60 percent.