TABLE OF CONTENTS
Chapter 1:
Program Overview
Chapter 2:
Tribal Legal And Administrative Framework
Chapter 3:
Lender Participation
Chapter 4:
Eligible Activities And Properties
Chapter 5:
Loan Processing And The Firm Commitment
Chapter 6:
Loan Closing And Endorsement
Chapter 7:
Administering Construction Loans
Chapter 8:
Loan Servicing
Chapter 9:
Alaska Processing Guidelines For Construction
Loans
Chapter 10:
Direct Guarantee
Chapter 11:
Refinances
LIST OF
APPENDICES
LIST OF
EXHIBITS
|
Chapter 9: Alaska Processing Guidelines for Construction Loans
|9.1 Overview
|9.2 Loan Terms And Requirements
|9.3 Costs Eligible For Inclusion In Mortgage
|9.4 Construction Period
|9.5 Administration During Construction
|9.6 Submission At Completion Of Construction
|9.7 Unforeseen Circumstances During Construction
9.1 |
OVERVIEW
As a result of unique logistical and market conditions which
exist in remote rural Alaska communities, the Alaska Office of
Native American Programs has developed this chapter in the Section
184 Indian Housing Loan Guarantee Program Guidebook for use by
lenders in originating new construction mortgage financing. Most
mortgage financing plans provide only permanent financing. That
is, the lender will not usually close the loan and release the
mortgage proceeds unless the condition and the value of the property
provide adequate loan security. When new construction is involved,
this means that a lender typically requires the construction to
be complete before a long-term mortgage is made.
When a borrower wants to have a new house constructed, the borrower
usually has to obtain financing to construct the new dwelling,
referred as an interim loan, and a permanent mortgage when the
work is complete to pay off the interim loan. Often interim financing
for new construction has been difficult to obtain and is a major
requisite in the delivery system for new housing in rural Alaska
communities.
The Section 184 Program was designed to address this situation.
Only one closing is used in the Section 184 Program. In the case
of a loan that includes new construction, an estimate of construction
costs, including a contingency allowance, is included in the loan.
At the time of loan closing the amount allocated for construction
is placed in an escrow account. The escrow account may also include
funds to cover up to six mortgage payments (PITI) to assist the
borrower in making monthly payments during the construction period.
The construction period is generally limited to nine (9) months
but a three (3) month extension may be granted.
Lenders may elect to offer separate construction and permanent
loans. However, under this election, only the permanent loan would
be guaranteed under Section 184. In such cases, the loan is treated
as an acquisition of an existing structure after construction has
been completed. Lenders may request a commitment for the borrower,
prior to making the construction loan.
The permanent loan guarantee will be honored by HUD in all circumstances.
Disqualification of lenders for failure to comply with requirements
is addressed in Chapter 3. |
|
back to top |
9.2 |
LOAN TERMS AND REQUIREMENTS
- Firm Commitment Requirements. For approval of a loan
guarantee prior to the construction period, additional documents
must be submitted by the lender in addition to those specified
in the processing guidelines, Paragraph 5.23c, as listed below:
- Construction Loan Agreement — This agreement
is between the lender and borrower and specifies the terms
during the construction period.
- Construction Loan Rider — This document amends
the mortgagee’s Deed of Trust or Security Deed between
borrower and lender which further covenant the terms of the
loan.
- Approved Builder — Name of the builder as approved
by the lender. Owner/Builders are not prohibited, but it is
recommended that the work be performed by a general contractor
registered to work as a contractor under Alaska Statutes (AS
08.18) with experience, qualifications and a track record of
similar work.
- Architectural Exhibits — The borrower may decide
to employ an architect or design consultant to prepare the
proposed construction documents. The borrower must provide
the lender with documents, which clearly describe the scope
of work and construction schedule. The following list of exhibits
are recommended:
- Plot Plan of the Site — Shows the location of the
structure with setbacks, driveways, water/sewer lines and
other relevant detail. Shows the flood elevation.
- Plans and Specifications — Shows elevations, floor
plan and sufficient details of materials and finishes to
direct the work. All work must be in accordance with local
building codes, as applicable.
- Schedule of Amounts for Contract Payments, form HUD-51000.
Shows construction loan breakdown by the contractor in sufficient
detail to guide construction drawdowns by the borrower. It
may be convenient to use columns (1) Item Number and (2)
Description of Item in the Period Estimate for Partial Payment,
form HUD-50001 or draw request form (Appendix 4) which would
be the basis for construction draws. It is important that
the lender analyze the breakdown in order to avoid "front
loading" of draws. (In some instances, lender may request
supporting bids from subcontractors and suppliers.)
- Construction Progress Schedule — Contractor’s
planned construction schedule to cover the period of time
from the starting date stipulated in the contract through
the date of actual contract completion. The schedule may
be computer or manual generated as long as the information
is realistic and accurate in a format providing acceptable
data. The lender may compare the schedule with periodic Compliance
Inspection Reports to monitor progress. If the lender finds,
as the work progresses, that there is or has been a slowdown
of construction, he/she shall discuss the matter with the
borrower and request that the borrower cause the contractor
to correct the undesirable condition and, if possible, to
recover the lost time.
- Homeowner/Contractor Agreement — Is between the borrower
and the contractor (optional) and specifies the terms of
the construction contract and incorporating the architectural
exhibits into the contract. At a minimum, the Agreement should
(1) describe the work to be performed; (2) state when work
will start and finish; (3) state the total amount to be paid
to the contractor and terms of payment; (4) provide provision
for binding arbitration on any disputes; and (5) provide
a one year warranty on all work completed by the contractor.
If the lender has determined the borrower has sufficient
experience to do the work or act as the general contractor,
the lender should obtain a Self-Help Agreement from the borrower.
- Timing. Loan closing must occur after the receipt of
a Firm Commitment and prior to the start of construction. Lenders
who close the loan or allow construction to begin before receipt
of the Firm Commitment, run the risk that errors could be found
in the underwriting criteria and the loan would be rejected.
Any funds spent on the rejected loan would not be guaranteed.
- Interest rate. The interest rate on the loan must be
a fixed rate for the term of the loan. Since the loan is fully
guaranteed, the rate should reflect market rates for permanent,
rather than construction financing.
- Compliance. Secondary mortgage lenders (investors) are
encouraged to be bonded, and require lenders who hold the construction
escrow account to be bonded to ensure compliance with their responsibility
to borrowers.
- Valuation. Appraisal procedures will comply with industry
standards by using the HUD Uniform Residential Appraisal Report
(URAR) format. The market data approach to value estimation should
be used where practicable. Generally, comparable sales should
be closed within the last 12 months preceding the date of the
appraisal, and should be within the community of the subject
property. In some rural areas of the state where there is a very
low inventory of housing, older sales may be used if adequately
explained. When adequate market data is not available, the cost
approach will be used and supported by the Marshall and Swift
Handbook or other acceptable source with comments provided to
explain all adjustments. For new construction, the appraisal
is made from a complete set of plans and specifications, which
will be incorporated into the loan as part of the Architectural
Exhibits and must provide a supported and defensible estimate
of value.
- Owner/Builder wages are not an eligible construction
expense. A borrower may act as his/her own general contractor;
however, he/she cannot be compensated for labor. The borrower
could not act as the actual trades contractor unless he/she
is skilled in that area.
- Building on own land. A homebuyer can use equity, which
they have created in the past, i.e., built foundation or the
on-site infrastructure, if the appraisal supports its value.
If the borrower is acting as a general contractor or is having
a house built on land already owned or being acquired separately,
maximum financing is available if the borrower receives no cash
from the settlement. (The lender must condition its approval
to assure cash is not received at closing.) The appropriate loan-to-value
limits are applied to the lesser of:
- The appraised value; or
- The acquisition cost of the property, which includes:
- The builder’s price or the sum of all subcontractors’ bids,
materials, etc.
- Cost of land. If the land was owned more than six months
or was received as an acceptable gift, the value may be
used instead of its cost.
- Lender fees and other costs associated with any construction
loan obtained by the borrower to fund construction of the
property.
- Allowable closing costs.
|
|
back to top |
9.3 |
COSTS ELIGIBLE FOR INCLUSION IN MORTGAGE
- Closing Costs. Allowable closing costs to be paid by
the borrower must be typical, reasonable and customary for the
area (as determined by HUD) and may include:
- Appraisal fee.
- Deposit verification fees.
- Document Preparation (if prepared by a third party not
controlled by the lender).
- Test Certification Fees (water or environmental tests).
- Settlement fees.
- Cost of title examination and title insurance.
- Consultant fees to prepare architectural exhibits.
- Property survey.
- Origination fee (1% of the mortgage amount before the
guarantee fee).
- Recording fees.
- Attorney fees (if the attorney is not an employee of the
mortgagee).
- Credit report costs.
- Loan Guarantee fee (1 percent of the principal obligation
of the loan).
- Lender Fees. Lenders may charge borrowers for typical,
reasonable, and customary fees associated with administering
construction. These fees may include charging the borrower for
the cost of construction inspections. In addition to the origination
fee, the Department will allow lenders to charge an administration
fee of up to two (2) percent for loans involving construction
advances. These are cost eligible for financing in the mortgage
(up to the LTV and the borrower’s debt to income ratio).
- Contingency Reserve. The construction cost estimate
must include a contingency reserve of at least 10 percent (see
Paragraph 7.3(b), which is intended to be held for unforeseen
circumstances during the construction period. Release of funds
shall be made through an approved change order request form,
Request for Acceptance of Changes in Approved Drawings and Specifications,
form HUD-92577.
- If the lender believes that a contingency reserve of more
than 10 percent is needed, the lender may require the borrower
to increase the amount but under no circumstances shall a contingency
reserve be more than 20 percent.
- Provided construction is progressing satisfactorily and
on schedule (minimum of 95% complete), funds in the contingency
reserve, which are anticipated to be remaining at completion,
may be approved by the lender for items other than unforeseen
circumstances (i.e., upgrades or improvements). However, lenders
should ensure funds are retained in escrow (an amount equal
to 1-1/2 times that estimated) for any uncompleted work before
authorizing depletion of the contingency reserve.
- Remaining funds in the contingency reserve at the Final
Release Notice stage may be used to reimburse costs to the
borrower for change orders, which resulted in an increase in
costs where the borrower placed additional monies into the
construction escrow account.
- Unforeseen construction costs in excess of the contingency
reserve must be paid by the borrower outside the mortgage agreement.
- Less than 10 percent contingency may be approved by the
Program ONAP on a case-by-case basis provided other risk sharing
considerations exist. For example, a construction contract
with a contractor who has obtained a materials and performance
bond on the work may justify a reduction of the contingency
reserve.
- Mortgage Costs During Construction Period. An allowance
for mortgage payments for up to six (6) months (including PITI)
can be included in the construction escrow account to enable
the borrower to make payments during the construction period.
- The mortgage must begin amortization with the first monthly
payment, whether or not construction of the property has
started.
- Mortgage payments may be withdrawn by the lender on a
monthly basis.
- If the construction period extends beyond six (6) months,
the borrower must begin to make mortgage payments from non-escrow
funds.
- For approved extensions, the borrower must begin to make
mortgage payments from non-escrow funds.
|
|
back to top |
9.4 |
CONSTRUCTION PERIOD
The construction period begins when the loan is closed. Construction
will be limited to nine months; however, an additional three-month
extension may be granted by the lender if the borrower and the
builder can provide adequate justification for the extension. Such
extensions will not affect the term of the mortgage nor can the
amount of the mortgage be increased to cover any cost overruns
associated with the construction delay. Extension requests should
be submitted for approval to the Program ONAP office. |
|
back to top |
9.5 |
ADMINISTRATION DURING CONSTRUCTION
Lenders participating in the program have a fiduciary responsibility
to administer new construction activities in a manner, which limits
the risks to the Section 184 program. Lenders must use due diligence
in assessing the information submitted and satisfy themselves that
the construction project as proposed can be met within time and
budget constraints.
Due diligence, for this purpose, is defined as compliance with
the processing requirements of the Section 184 Indian Loan Guarantee
Program, maintaining accurate and appropriate accounting records,
and using prudent contract administration judgment. Lenders who
do not exhibit due diligence or have not taken active steps to
prevent the occurrence of a default may be exempted from further
participation in new construction loan activities.
If a builder defaults during the construction period, lenders
are expected to work with the borrower and the builder to try to
resolve the problems leading to default, rather than choosing the
early assignment option. Because mortgage payments due during the
construction period are included in the construction escrow account,
the builder default should not lead to a borrower payment default,
unless the builder’s default extends beyond the period for
which mortgage payments have been reserved. Therefore, a lender
should assign a Section 184 construction mortgage to HUD only after
the borrower fails to make three mortgage payments from his or
her own funds. HUD will then be responsible for the foreclosure
proceedings.
Upon closing of the loan, the lender shall provide for:
- Construction Escrow Account. Proceeds designated for
construction (including the contingency reserve and the mortgage
payment reserve) should be deposited in an interest-bearing account
insured by the Federal Deposit Insurance Corporation (FDIC) or
the National Credit Union Administration (NCUA). The construction
escrow account must be fully funded at loan closing. The interest
income earned by the Construction Escrow Account must be paid
to the borrower or applied to the unpaid principal loan amount.
Payment is subject to agreement between the lender and the borrower.
- Builder Insurance During Construction. The builder
must have builder’s risk insurance in an amount equal to
or greater than the total mortgage amount. In addition, the builder
must have liability coverage against injury or death to others
who may enter onto the job site and workmen’s compensation,
which at a minimum will provide liability coverage for any persons
working on the job site. Once the improvements have been fully
completed or the borrower occupies the property (whichever comes
first), the borrower must have in place hazard insurance. If
applicable, the borrower must also have flood insurance. When
these required policies go into effect, the builder’s risk
may be cancelled.
- Inspections During Construction. All construction inspections,
including the final inspection, must be performed by a qualified
inspector, who is a disinterested third party and cannot be personally
or financially related to the builder, borrower or other interested
party, as approved by the lender. Local Indian Housing Authority
(IHA) staff may do construction inspections if they are qualified
and acceptable to the lender, except when the lHA is the borrower.
Construction inspection fees are considered a construction
cost and should be paid from the borrower’s loan funds by
the lender and included as part of the total price of the home.
Due to high transportation costs for on-site inspections in
remote locations, 60 percent of the inspections (excluding the
final inspection), may be completed by video, including narrative
in the format approved by the lender to ensure adequate coverage
of the work completed. The video should be taken by a disinterested
third party and must be fully representative of all work performed
for which the purpose of the inspection is being conducted.
Improvements must be satisfactorily completed in compliance
with industry standards to the satisfaction of the inspector.
Any deficiencies must be expeditiously corrected and noted in
the subsequent report. The inspector must confirm the percentage
of completion in accordance with the approved architectural exhibits.
When acceptable, the inspector completes a Compliance Inspection
Report, Form HUD-92051 and sends it to the lender for review.
The lender may determine that additional compliance inspections
are required throughout the construction period to ensure that
the work is progressing in a satisfactory manner.
- Release of Funds from the Construction Escrow Account. The
lender may not release funds from the Construction Escrow Account
until the lender has received a Compliance Inspection Report,
form HUD-92051, and the draw request form, Periodic Estimate
for Partial Payment, form HUD-51001, certifying that the work
has been completed in compliance with the accepted plans, specifications
and architectural exhibits. Allowable fees paid by the borrower
or on the borrower’s behalf may be reimbursed provided they
are listed and documented. Under no circumstances is a payment
request to be approved for work that is not yet completed, with
the exception of a payment for materials and shipping costs.
It is the responsibility of the lender to obtain written approval
from the borrower before each draw payment is provided to the
builder.
- Materials and Shipping Costs. The lender may disburse
payments for building materials or components to be shipped
and stored on site provided satisfactory evidence that:
- The borrower has acquired title to the material as necessary
to perfect the lender’s lien;
- Prior to shipment, the material is stored and protected
from weather in a bonded-storage yard or other suitable place
as may be approved by the lender;
- The material is insured to cover its full value; and
- The material will be used for this contract.
Before any progress payment, the lender shall obtain such
documentation as required to assure the protection of the borrower’s
interest in such materials. A progress payment may be made
for up to 90 percent of the invoiced building materials value,
including shipping costs. For approval, lenders must attach
original invoices to a listing of the materials on the Schedule
of Materials Stored, form HUD-51003 which corresponds to the
arrangement established on the Schedule of Contract Payments,
Form HUD-51000. Also, required documentation must include a
Bill of Lading verifying that the materials have been accepted
by the shipping agent, proof that transportation or marine
insurance is sufficient to cover any loss materials in transit
and execution of a Security Agreement and UCC-1 as necessary
to perfect the lender’s lien.
The lender must require an acknowledgement of payment and
releases of liens from the contractor, all subcontractors and
suppliers. The first deed of trust on the property may serve
as security on the materials. Only if the subject property
is not available to use as collateral may other real or personal
property be considered for use as collateral. The remaining
10 percent may be paid upon arrival of materials, once inventoried
on-site. Borrowers are responsible that the materials are sufficiently
protected from weather and loss once delivered on-site. Any
damage or loss sustained not recoverable through insurance
is the responsibility of the borrower.
- Number of Progress Payments. Generally no more than
10 construction payments should be made, approximately one
per month, on the escrow account. The lender or its agent will
release escrow funds only upon satisfactory completion of the
proposed construction, pursuant to the Loan Agreement.
- Retain on Draws. A ten percent (10%) holdback is required
on each release of construction funds except those approved
in advance for shipping materials in d(1) above. Use of the "Computation
of Balance Due This Payment" on the backside of the draw
request form HUD-51001, Periodic Estimate for Partial Payment,
will reduce the amount of materials stored as they are incorporated
into the work. The total of all retainage may be released only
after the final inspection and issuance of the Final Release
Notice.
- Change Orders. The change order request form, Request
for Acceptance of Changes in Approved Drawings and Specifications,
form HUD-92577, shall be prepared by the borrower or builder
for all changes to the Architectural Exhibits, and must be submitted
to the lender for prior approval. Work must be 100 percent complete
on each change order item before the release of any monies to
the borrower or builder.
- If the change order results in an increase of costs, the
borrower must place additional monies into the construction
escrow account for payment upon acceptance of the change.
- If a change order results in a decrease of costs, the difference
cannot be released and will be applied to prepay the mortgage
principal after completion of the work.
- If a change order results in both an increase and decrease
of costs which the offset cumulatively totals more than 10
percent of the loan, a revised appraisal must be completed
to ensure the value has not decreased.
- Extensions. If the work is not completed within the
time frame, the borrower and builder must request an extension
of time on the change order request form, Request for Acceptance
of Changes in Approved Drawings and Specifications, form HUD-92577,
and provide adequate reasons to justify the extension. If acceptable,
the lender should verify the status of the work and may order
an additional compliance inspection of the property.
- Final Inspection. When all work has been completed,
the borrower must submit the Periodic Estimate for Partial Payment,
form HUD-51001, marked "Final" and provide a Mortgagor’s
Letter of Completion, requesting a final inspection and indicating
all work is satisfactorily complete. Upon receipt, the lender
will schedule an inspection. The inspector must visit the site,
determine whether the work was completed according to the approved
architectural exhibits/changes orders and complete the Compliance
Inspection Report, Form HUD-92051. The document must be accompanied
with photographs representative of the work completed. Exterior
photographs showing site work, all sides of the dwelling and
the interior are required. If the final inspection discloses
any minor punch list items that do not affect health/safety or
livability and occupancy of the dwelling, and circumstances such
as weather conditions prevent timely completion, the inspector
will so certify and identify each item and its associated value
to complete the Compliance Inspection Report and provide the
report to the lender.
- Closeout. After a review of the case file to ensure
that all work has been completed, the lender will obtain from
the principal contractor(s) lien releases to the date of the
final payment for all work done, labor performed, and materials
and equipment provided. If a Certificate of Occupancy is required
by the local governmental jurisdiction, it must be submitted
with the lender’s transmittal. The lender will prepare a
transmittal to the HUD Program ONAP identifying any unused construction
funds or contingency reserves to be applied to the principal
balance of the mortgage along with a copy of the "Final" Compliance
Inspection Report, form HUD-92051. If the "Final" Compliance
Inspection Report lists any punch items the lender will be required
to retain in the escrow account an amount equal to 1-1/2 times
that estimated to complete the work. The lender must complete
the Mortgagee’s Assurance of Completion, form HUD-92300,
and submit PART 1 and PART 2 to HUD. This work is normally limited
to 180 days and may be verified by videotape or photographs.
Once all work is completed the lender will complete PART 4, certifying
all items have been completed in a satisfactory manner.
- Final Release Notice. If the HUD Program ONAP accepts
the "Final" Compliance Inspection Report, a Final Release
Notice will be issued which authorizes the release of all monies
remaining in the Construction Escrow Account, including all retainage,
with the exception of any held for uncompleted work. The lender
may retain a holdback, for a period not to exceed 35 days or
the period required by state law to file a lien, whichever is
longer. A copy of the final inspection report and the Final Release
Notice shall be given to the borrower.
|
|
back to top |
9.6 |
SUBMISSION AT COMPLETION OF CONSTRUCTION
Within 30 days of the issuance of the Final Release Notice, the
lender shall submit the following documentation to HUD:
- Warranty of Completion of Construction, form HUD 92544. Contractor’s
one-year warranty of work and materials. Required only when a
general contractor is performing the work.
- Compliance Inspection Reports. All reports, form HUD-92051,
signed by the inspector.
- As-built drawings. A set of as-built drawings from information
maintained and provided to the lender showing all approved changes
noted on a set of the original plans. Also, include the as-built
survey showing the house location within the lot.
- Periodic Estimate for Partial Payments, form HUD-51001. Copies
of all draw requests or Periodic Estimate for Partial Payments
showing the amount(s) and to whom disbursements have been made.
- Mortgagor’s Letter of Completion. Borrower certification
that construction has been completed in a workmanlike manner
in accordance with the plans and specifications and approved
change orders, if any.
- Certificate of Occupancy, as applicable.
- Final Release Notice. Authorization for release of the
final draw and all retainage, including instructions on prepaying
the mortgage with any remaining escrow funds.
|
|
back to top |
9.7 |
UNFORESEEN CIRCUMSTANCES DURING CONSTRUCTION
Construction activities in rural Alaska communities are high-risk
ventures with many pitfalls awaiting the participants. Lenders
participating in the Section 184 Indian Loan Guarantee Program
are expected to use due diligence and care in the administration
of new construction loans. However, even with the utmost care and
attempts to mitigate unforeseen circumstances, a lender may find
that the construction cannot be completed with the funds available.
Under such circumstances, the lender must assess all the factors
and make a choice between two courses of action:
- Occupancy of Property. A dwelling exhibiting all required
living amenities may have certain areas that are unfinished or
incomplete. Typically, in new construction, the owner may purposely
leave the lower level of a split entry dwelling unfinished, since
it is not obvious from the habitable area or the exterior of
the dwelling and it would be acceptable for financing.
Notwithstanding an event where the property is less than 100
percent complete based on the plans and specifications, the contingency
reserve is depleted, and the borrower has exhausted their resources
and credit limits, the lender may determine that the property
is habitable for possession by the borrower.
A lender-selected inspector will conduct a "final inspection" to
review the property to determine its habitability. Punch list
items and their value will be compiled for submission to the
lender.
- If it is determined that the property meets the minimal
standards, a punch list of items required to achieve 100 percent
completion is provided to the lender. Depending on the nature
of the items, the lender should determine if the borrower,
given additional time, has the capability or the resources
of providing "sweat equity" to complete the dwelling.
Notice and prior approval of the Program ONAP is required.
- Lender must counsel the borrower about their obligations
and encourage fulfillment of their responsibilities.
- Borrower must agree to accept the mortgage amount despite
the reduced value of the unfinished property.
- Punch list items must meet the plans and specifications
as originally approved and upon which the appraised value
is based. Work should be completed within two years of final
inspection. The lender assumes the responsibility to verify
that the punch list items have been completed.
- Minimal Habitability Standards
- There must be no health and safety hazards, which create
a threat to occupants.
- Major interior and exterior work must be completed; exceptions
could be work not affecting the beneficial use of the dwelling.
- Plumbing must comply with the minimal standards established
by the applicable tribal, borough or state authority.
- There must be permanently installed appliances, including
a range/oven and refrigerator.
- Heating systems must have the capacity to maintain a minimum
temperature of 65ºF during the coldest weather in the
area.
- Electrical system must supply energy requirements for
lighting and operation of appliances.
- Default and Subsequent Assignment. If the work is not
started within 30 days or if the work ceases for more than 30
days or is not progressing reasonably and according to schedule,
the lender may consider the loan to be in default. In the event
of a default and subsequent assignment of the mortgage during
the construction period, lenders must send a letter to HUD. This
letter should describe, in sufficient detail, the events which
led to the default, balances owing and funds remaining in the
escrow account. The lender should request a final inspection
of the property to compensate the contractor for all work completed
through the date of assignment.
- Final Inspection. The HUD Program ONAP will assign
an inspector to review the property. The inspector will use
the Compliance Inspection Report and the draw request form
or Periodic Estimate for Partial Payment to document the amount
or work that has been completed since the start of construction
and determines the value of the completed work to authorize
release of escrow funds. Additionally, the inspector will itemize
the work necessary to complete construction and the estimated
cost.
- Final Release. HUD will authorize release of payments
for completed work, as well as the release of any retainage.
Lender should request a Final Release Notice with a claim for
loan guarantee benefits. If funds remain in the escrow account,
the amount of the claim must be reduced by the funds remaining.
|
|