Date: December 2, 1996 (Rev 1)
Letter No. LR-96-03
Subject:
Application of Department of Labor guidance concerning "projects
of a similar character".
I.
DOL All Agency Memoranda #130 and #131.
II. Definitions: "Incidental" versus "substantial".
III. HUD policy and practice.
IV. Considerations for residential construction.
V. Mixed-use projects.
VI. Important Notes about Multiple Schedules.
VI. Case Studies.
U.S.
Department of Labor (DOL) All Agency Memoranda (AAMs) #130 and #131
provide guidance as to identifying character of work (e.g., building,
residential, heavy, highway) for the purpose of applying Davis-Bacon
wage determinations. These memoranda are focused primarily toward
public improvements such as water and sewage treatment plants and
roadways rather than housing development projects. Questions, however,
are raised from time to time concerning the application of AAMs
130 and 131 to HUD housing programs. The purpose of this Letter
is to review the DOL policies in the context of HUD programs, in
particular housing development.
The following is provided with the cooperation and advice of the
DOL.
I. DOL All Agency Memoranda
AAM 130 provides definitions for four (4) broad categories
of construction: residential; building; heavy and highway. AAM 130
generally states that a "project" is classified as belonging
in one of the 4 categories and that a "project"
would consist of all construction necessary to complete a facility.
In a footnote, AAM 130 states that a multiple classification may
be appropriate if there are substantial portions of the project
that would fall into different categories (e.g., building and
heavy).
AAM 131 provided clarification to AAM 130 by explaining that a literal
application of AAM 130 guidance may be inappropriate in certain
cases. AAM 131 emphasizes in particular the complexities inherent
in the application of multiple wage schedules and cautions that
agencies should proceed with multiple schedules1
only after advance consultation. It is further stated that area
practice is determinative for any question about the proper classification
of construction.
We would note that the primary thrusts of AAM 130 and 131 are not
to advise on the issuance of multiple schedules or to define "incidental"
or "substantial". The overall purpose of these AAMs is
to ensure the appropriate selection of the one category of
construction that best suits the proposed work. We would also note
that none of the examples given in AAM 130 or 131 where multiple
schedules might be appropriate is a housing project.
II. Definitions: "Incidental" vs "substantial"
Incidental
items do not alter the overall character of the project but are
installed for the purpose of the total project to which they relate
in function. Incidental items are subject to the same wage schedule
that applies to the overall project.
In addition to "incidental" relative to function, AAMs
130 and 131 discuss "incidental" relative to cost. Twenty
percent of the project cost is offered as a rough guide for what
is "incidental" in relation to the overall project, which
would not warrant a multiple schedule.
Substantial
is defined in terms of relative cost: more than 20% of the
total project cost. In recognition that very large projects may
contain components of a different character that may be sufficiently
"substantial" to warrant a separate schedule even though
these components may not exceed 20% of the total project cost, a
$1 million or more absolute cost was offered as a supplementary
guide to help define "substantial."
III. HUD policy and practice.
HUD policy and practice is consistent with AAMs 130 and 131 in that
HUD seeks to identify the (one) category of construction that best
suits the proposed work and issues the (one) corresponding Davis-Bacon
wage determination. Most HUD-assisted projects fit cleanly in a
single construction category and incidental items are not "substantial."
As a result, the issuance of multiple schedules has been rare for
HUD-assisted construction projects and would represent a departure
from the norm. (Some geographic areas may experience more multiple
schedule activity because, for example, DOL wage decisions for heavy
and highway construction are issued separately.)
IV.
Considerations for residential construction
Residential construction is defined in AAM 130 as projects "involving
the construction, alteration, or repair of single family houses
or apartment buildings of no more than 4 stories in height. This
includes all incidental items such as site work, parking areas,
utilities, streets and sidewalks" (emphasis added).
The primary component, which determines the character of the project
and the type of wage schedule that applies, is the housing. Elements
such as site work, parking areas, etc., are incidental in
that their purpose is to support the housing. Other items which
may be incidental to housing construction include swimming pools,
community buildings, storage sheds, carports and on-site management
offices. However, such items constructed alone, without accompanying
housing construction, would be the primary component and, accordingly,
the character of the project and the type of wage schedule that
applies would be determined on that item alone.
Recently on some projects involving housing development it has been
estimated that the cost of certain incidental items such as site
improvement might exceed the DOL guide for "substantial"
by absolute or relative cost. The mere existence of cost that may
be "substantial," however, does not justify the use of
multiple wage schedules.
Generally, any housing development project (4 stories or less) is
classified as "residential." This classification is not
altered by the cost of incidental items, even if such costs exceed
the guide(s) for "substantial." Except in the most extraordinary
circumstances, such as where local industry practice clearly demonstrates
otherwise, only residential wage schedules shall be issued for housing
development projects. Multiple schedules shall not be issued because
of the incidental items noted above and other similar items. HUD
Field Labor Relations staff shall consult with the appropriate Headquarters
Labor Relations representative in advance where the issuance of
multiple schedules is contemplated for a housing development project.
V.
Mixed-use projects.
Mixed-use projects are those which contain elements of different
construction characters but these different elements are
not incidental to each other2.
Examples include a housing project that contains both low-rise and
highrise buildings; and a 4-story apartment building with commercial
space on the first floor. The different elements in these cases
are components that each have their own purpose - they are not merely
supportive of another element's function. Therefore, multiple schedules
are appropriate where mixed-use projects are involved.
VI.
Important Notes about Multiple Schedules:
- The
project/contract specifications must clearly delineate the portions
of the project subject to each wage decision issued.
- All
wage decisions must be posted at the job-site with an explanation
as to where each wage decision applies.
- The
developer/prime contractor must agree to establish adequate
controls to ensure that all laborers and mechanics are paid
in accordance with the wage schedules.
- All
employers (contractor, subcontractors, lower-tier subcontractors)
must agree to prepare, submit and maintain accurate employee
time and payroll records to demonstrate compliance with all
wage decisions applicable to the project.
- Use
of multiple schedules is contingent upon the agreement and compliance
with these conditions.
VI.
Case studies.
The following examples illustrate how the guidance in this Letter
may be applied to various situations. And, how timely Labor Relations
advice may relieve contractors and contracting agencies from inordinate
administrative burdens. A description of the project is followed
by the wage determination issuance decision and rationale.
1. a. Project The project involves the new construction
of 60 family units in three 3-story walk-ups and 50 elderly units
in a highrise building; other improvements include clearing and
grading, streets, sewers, utilities, play areas, driveways, parking
areas.
b. Decision Separate wage decisions, residential for
the walk-ups and building for the highrise, may be issued
for the construction of the buildings. These are distinguishable
components which are substantial in their own right; neither can
be considered "incidental" to the other, therefore,
multiple wage decisions are issued provided that the contractor
agrees to comply with the recordkeeping requirements in paragraph
V above.
The site improvements must be considered as well. Since the improvements
are incidental to the construction of the housing a separate wage
decision need not be issued. To the extent that certain site improvements
can be demonstrated to serve the walk-up buildings rather than
the highrise building (e.g., parking areas, sidewalks, play areas
dedicated to the family units) those site improvements may be
completed under the residential wage decision. The remainder of
the improvements, i.e., those dedicated to the highrise and those
common to both the family and elderly units must be completed
using the building wage decision.
2. a. Project The project involves the rehabilitation of
two large 4-story buildings containing retail/office space on
the first floor and residential units on the upper floors. The
residential units will each receive new interior walls, windows,
doors, carpet, fixtures, appliances, and other finishings. Work
in the retail/office spaces will include some electrical and HVAC
upgrades, new windows, doors and other exterior finishings consistent
with the improvements to the residential units. This work in the
retail/office spaces represents 10% of the total rehabilitation
costs on these structures.
b. Decision A single residential wage decision is
issued for all work performed on the two 4-story buildings. Work
on the first floor interiors and exteriors is incidental to the
rehabilitation work on the upper three floors. This finding of
incidental is additionally confirmed because the lower floor work
represents less than 20% of the rehabilitation costs.
3. a. Project Assume the same project described in example
#2 and add a 3-story parking garage that will be newly constructed
adjacent to the two 4-story buildings to serve the residential
and retail/office tenants, as well as hourly parking for the general
public.
b. Decision The rehabilitation work would still be performed
under a single residential wage decision. However, the parking
garage would be subject to the building wage decision.
The garage cannot be considered to be incidental to the rehabilitation
work. The garage is substantial in its own right and has as its
purpose a service well beyond the residential or retail/office
tenants.
4. a. Project A public housing authority (PHA) has undertaken
a 3 year comprehensive improvement program, e.g., CIAP project,
at one of its larger family developments consisting of several
4-story walk-ups. The total program will involve rehabilitation
to all of the housing units in varying degrees. For example, some
units will require only cosmetic repairs and minor replacements
which can be classified as nonroutine maintenance; other units
will require extensive repairs including some "gut rehab,"
and others are being converted to accommodate larger families
(e.g., 2-bedroom units grouped and converted into 5-bedroom units).
Other improvements include sidewalk repairs, curb and gutter replacement,
parking lot expansion and the installation of a security fence.
The PHA has divided the "program" into phases so that
the work will be more manageable and to minimize disruption to
the residents. The first contract will be awarded for the security
fence installation. Immediately thereafter, the PHA will advertise
and award a contract for all of the rehabilitation work. The PHA
is considering using its own work force to perform some of the
work. The PHA sends a request for wage determination to the Labor
Relations staff describing the work as "installation of security
fence".
b. Discussion and Decision For this example, there
could be several "right" answers. It would be correct
to issue a heavy wage decision if the scope of work is
limited to a security fence. The PHA's wage decision request and
Labor Relation's response, however, may be shortsighted.
For example, if the PHA had grouped the security fence with a
portion of the rehabilitation work (which calls for a residential
wage decision), the security fence could be incidental to the
residential work and performed under the same residential wage
decision rather than a heavy wage decision (which often contains
much higher wage rates). The same would be true for the sidewalks
and other infrastructure improvements: combined with the rehabilitation
work on the housing units, the infrastructure could be incidental
to the residential work and performed under the same wage decision3.
Client agencies may not fully grasp the impact of "phasing"
and/or "packaging" certain work items. Labor Relations
staff can play a significant role assisting client agencies, like
PHAs, to plan work activities to its best advantage.
In this example, Labor Relations could suggest to the PHA that
the work items be grouped as described above to secure residential
wage rates for those activities. In addition, since the PHA is
contemplating using its own maintenance workers (i.e., force account)
to perform a portion of the work, the most logical activities
for this force account crew are those that can be characterized
as nonroutine maintenance. These activities will be subject
to HUD-determined wage rates which oftentimes are closely related
(or even based upon) the maintenance wage rates issued to the
PHA. Since PHA force account workers must receive no less than
whatever rate is applicable to the type of work they perform,
the potential similarity of these wage schedules (maintenance
and nonroutine maintenance) may result in less administrative
burden to the PHA.
5.
a. Project A PHA submits a wage determination request for minor
repairs and replacements in 20 housing units which can be characterized
as nonroutine maintenance; however, two of those units also require
more extensive repairs that exceed nonroutine maintenance parameters.
b. Decision There are two options available to the Labor Relations
staff and the PHA. Following consultation and depending on the PHA's
local circumstances and its own needs, all of the work may be performed
under the appropriate Davis-Bacon wage decision (residential or
building depending on number of stories, etc.) or the two units
needing extensive repairs can be separated from the nonroutine maintenance
work and be performed under a Davis-Bacon wage decision while the
nonroutine maintenance is performed under a HUD-determined wage
schedule. (Note advance consultation requirement for multiple schedules.)
Work items that require Davis-Bacon wage rates shall not be considered
incidental to other work subject to HUD-determined wage rates.
Any questions concerning this Letter may be directed to the Office
of Labor Relations at (202)708-0370 or, in the case of HUD program
participants, to the HUD Field Labor Relations Staff with jurisdiction
for your area.
Visit the Office of Labor Relations
on the World Wide Web HUD Home Page.
- Multiple
schedules refers to the practice of issuing more than one Davis-Bacon
wage determination for separate and distinguishable items in
a single project. These items may be incidental in function
(e.g., paving of roadways for a building project) but are so
substantial in relative or absolute cost as to warrant a separate
wage schedule(s) from that which is issued for the primary project
component.
Multiple schedules may also be appropriate where separate and
distinguishable items are not incidental in function and/or
cost. For example, a single new construction housing project
that contains both highrise and low-rise buildings. These buildings
are not incidental to each other but each serve a separate purpose
and would generally warrant both building and residential wage
determinations.
- Before
issuing multiple schedules, be certain that the proposed covered
construction work involves more than one classification of construction.
In some cases a project that involves a mixed-use property
may involve only one classification of construction, e.g., only
the residential units as in the sample building with commercial
space on the ground floor. If the proposed work only involves
rehabilitation of the residential units and no work in the commercial
space, only a residential wage schedule should be issued.
- This
"packaging" is not evasive of Davis-Bacon requirements.
These work items represent components of the residential development
and would have been subject to residential wage rates when the
project was first constructed. The components remain an integral
part of the development and continue to serve the housing and,
in a broad context, remain incidental to the overall residential
character.