This
information is posted in compliance with Federal Acquisition Regulation
(FAR) 52.102(c)
Subpart
2404.8--Government Contract Files
2404.805
Storage, handling and disposal of contract files.
(a)
Unsuccessful cost and technical proposals shall be retained in the
contracting activity for a period of two months following the contract
award as reference material for debriefings. Upon expiration of
the two month period, the contracting office shall either:
(1)
Retain one copy of each such proposal with the official contract
file; or,
(2)
Ship one copy of each unsuccessful bid or proposal to the Federal
Records Center unless a debriefing has been requested but not held,
or a protest is pending concerning the procurement. In no event
shall these documents be destroyed before expiration of the retention
periods in FAR 4.805.
(b)
By the program office. Unsuccessful proposals shall be retained
on file in the program office which conducted the technical evaluation
for a period of two months following the contract award. Upon expiration
of the two month period, the program office shall return one copy
of each unsuccessful bid or proposal not required for the conduct
of debriefings to the contracting activity for proper disposition.
The remaining copies will be destroyed.
|