|
The
Construction / Rehabilitation Costs portion of the Development
Costs tab should cover all costs included in a construction
contract:
-
Other Site Work includes only costs included in the construction
contract, usually a set of standard items that are required to
prepare the site for construction or to put it in usable condition
after construction is complete. Any additional or atypical site
work should be entered under Site
Work Costs.
- New
Construction refers to the cost of labor and materials for
the construction of new housing units.
- Rehabilitation
refers to work on existing structures, such as installing new
plumbing, facade improvements, installing new appliances, treating
lead-based paint hazards etc.
- General
Requirements
refers to an allowance for the contractor's on-site overhead expenses.
General requirements typically include building permits, fencing
around the site, temporary storage for materials, construction
supervision, the "job trailer," and temporary utilities.
- Builder's
Overhead
is an allowance for the portion of the builder's off-site (home
office) overhead that is attributable to the project.
- Builder
Profit
is typically based on the size of the project, the total development
cost and the risk associated with the project. This cost is expressed
as a percentage of construction costs in the Other Information
column.
- Performance
Bond Premium
refers to the cost of a performance bond. By issuing a performance
bond, a bonding company commits to completing the development
project in the event that the original contractor defaults on
its contractual obligations. An estimated performance bond premium
can be obtained from a bonding company. Federal rules (24 CFR
Part 85.36) require bonds for 100 percent of a contract value
for all contracts over $100,000.
- Construction
Contingency refers to funds held to account for cost overruns.
Weather changes in the planned construction are among the many
factor that can lead to cost overruns. Be sure an up-front agreement
is made about how any remaining construction contingency funds
will be distributed after project completion. The construction
contingency is expressed as a percentage of all construction costs
under the Other Information column.
- Use
the Other Construction / Rehabilitation Costs field to
enter costs related to construction and rehabilitation that are
not represented by the other items in this category. Enter a label
(replacing the "Other Construction / Rehabilitation Costs"
text) and an amount. If you do not need to use this field, simply
leave it blank.
|