Architectural
fees should be based on an estimate or on an actual agreement with
the architect. These fees may be structured as a percentage of the
construction contract amount, a fee per dwelling unit, a flat fee
for services, or some other basis.
There
will always be two architect fees: one for the design of the buildings
and another for construction supervision. In this portion of the
Development Costs tab, enter the amount of the two architect
fees under Architect Fee - Design and Architect Fee -
Construction Supervision. Note that the architect handling design
and the architect supervising construction may or may not be the
same.
The
Engineering Fee estimate should include any mechanical or
structural engineering costs not incurred as part of the site plan
design fee. Note that the cost of an environmental survey and soil
boring are not included in this amount. These costs are entered
separately under Other
Owner Costs.
Use
the Other Architectural and Engineering Fees field to enter
costs that are not represented by the other items in this category.
Enter a label (replacing the "Other Architectural and Engineering
Costs" text) and an amount. If you do not need to use this
field, simply leave it blank.
|